# Project Name Start End Word Project Type Amount Latest Status Progress
21 Fill in front of Alipurd community clinic. 06-06-2017 18-07-2018 03 gr ৬০,২০০/- বাস্তবায়িত
22 Restoration of road adjacent to Ajaagra South Para Bhuiyan house. 14-06-2017 11-07-2018 04 lgsp ৬০,২০০/- বাস্তবায়িত
23 Construction of drain culvert on the north side of Alipur North Choukidar house 06-06-2017 18-07-2018 03 lgsp ১,০০,০০০/- বাস্তবায়িত
24 Pipe culvert construction of Uruk small fakir house. 20-06-2017 19-06-2018 05 grameenroad ৬০,২০০/- বাস্তবায়িত
25 Cottonseed of the remaining part of Baitun Nur Jami Mosque Rasarka, in Uruk Bazar, is CCC. 14-06-2017 26-06-2018 05 lgsp ৮১,০০০/- বাস্তবায়িত
26 Road reform on the north side of Kulsi Haji Houses 05-06-2017 27-06-2018 lgsp ৯০,০০০/- বাস্তবায়িত
27 Construction of the southern side of the Shibpur rail line on the road of Haripur mother house and construction of the drain. 20-06-2017 04-07-2018 07 lgsp ৮০,৫০০/- বাস্তবায়িত
28 Road reform from Uruk Thakur Market Road to Tum Idris Kari Bhaban. 12-06-2017 27-06-2018 lgsp ৬০,২০০/- বাস্তবায়িত
29 Provide access to arsenic free water connections in the east and west communities. 13-06-2017 27-06-2018 08 lgsp ১,৬৭,৭৫৬/- বাস্তবায়িত
30 Road reform from the bridge on the north side of Bhatunichola Munshi house to Tomta Sahib Bazar. 14-06-2017 20-06-2018 09 lgsp ৬০,২০০/- বাস্তবায়িত
31 Road reform from the south of the Krishnapur Shahaji house to the Bilal house. 06-06-2017 20-06-2018 09 lgsp ৬২,০০০/- বাস্তবায়িত
32 The restoration of the road to Ferheghat from Tamta (P) Para Bhuiyan House. Connection Mia Mosque Mosque 20-06-2017 18-07-2018 ০৮ kabita ২২,৩০০/- বাস্তবায়িত
33 Alipor Haji Bari Jami Mosque from Munshur Ali Haji Bhaban link to Haji Bhati from BD. Construction / reconstruction of road up to Aar's house 13-06-2017 12-06-2018 ০৩ kabita ২,৬৫,০০০/- বাস্তবায়িত
34 Construction of road from Alipur Mumin House to Tarafdar House. 13-06-2017 19-06-2018 03 থোক বরাদ্দ ৪,১৮,০০০/- বাস্তবায়িত
35 Culver building between Dhaypalla Chaiyal Ghar and Mia house 20-06-2017 19-06-2018 2 grameenroad ৭১,৭৮২/- বাস্তবায়িত
36 Culver construction in the Azagra street 20-06-2017 15-05-2018 ৪ নং ওয়ার্ড grameenroad ১,০০,০০০/- বাস্তবায়িত